Key Technology for Construction of Steel-concrete Composite Suspending Cofferdam without Bottom Cover for Platform of Coastal Intercommunication Project

LI Hong wei

Article ID: 2585
Vol 2, Issue 2, 2022
DOI: https://doi.org/10.54517/vfc.v2i2.2585
VIEWS - 28 (Abstract)

Abstract

Many bridge piers were built in the Coastal Interconnection Project of the Ningbo Section of the Hangzhou-Ningbo Expressway Double Line. Affected by the tides at the bridge site, the high pile caps are constructed using a suspending cofferdam without a bottom cover. Based on the consideration of various factors such as construction difficulty, safety, cost and construction period, etc. A cement structure is generally adopted as the floor of the suspended box cofferdam. The steel-concrete combined hanging box cofferdam without bottom cover adopts the structure of steel wall plate and prefabricated cement floor, and the partition wall plates are connected by bolts. The steel-concrete composite suspending cofferdam adopts the prefabricated bottom plate and wall plate. The construction sequence is listed as follows: First, weld the load-bearing corbel on the steel casing, and then hoist the prefabricated bottom plate to the steel casing corbel in blocks. Pour the wet joint between the prefabricated bottom plate and install the side plate. After that, pour the cushion after welding the shear plate. Finally, carry out the construction of the cap. During the construction of the project, the connection method between the wall plate and the bottom plate was optimized. The connection of the fine-rolled rebar hanger rod was changed to the steel bar pair pulling, which improved the construction efficiency significantly.


Keywords

Tidal area; High pile cap; Steel-concrete composite hanging box cofferdam without bottom cover; Construction optimization.

Full Text:

PDF



References

1. Lv Zhenguo, Zhu Ruiyun. Precise positioning and flood crossing technology of steel cofferdam for Ma'anshan Yangtze River Highway Bridge [J] Bridge Construction, 2014, 44 (4): 9-14.

2. Han Xiaojun. Construction technology for overall hoisting of large steel-concrete composite suspension box cofferdam [J]. Transportation Technology, 2015 (2): 45-47.

3. Chen Juanling. Design and construction of single wall steel-concrete composite suspension box for the main pier cap of Baisha No.1 Bridge [J]. Highway Transportation Technology, 2015 (7): 201-203.

4. Luo Jiulin. Design and overall lifting method research of single wall steel-concrete composite suspension box cofferdam in complex sea areas [J]. Railway Construction Technology, 2016 (1): 20-24.

5. Li Yi. Application of Unsealed Steel Concrete Composite Suspended Box Cofferdam in Deep Water Bearing Platform Construction [J]. Railway Construction Technology, 2017 (12): 56-59.

6. Ru Qijiang, Liu Chenggang, Du Xiongwei, et al. Key Technologies for Construction of Steel Concrete Composite Suspended Box Cofferdams with High Pile Caps in Shallow Sea Areas [J]. Railway Architecture, 2016 (3): 54-57.

7. Zhang Xufeng, Fang Xing, Wang Jingyu, et al. Construction of Bottom Steel Concrete Composite Suspended Box Cofferdam Platform in Tidal Areas [J]. Highway Transportation Technology, 2017 (10): 175-179.

8. Zhang Guangtao. Comparative study on the lowering process of steel-concrete composite suspension boxes in special marine environments [J]. Railway Construction Technology, 2018 (4): 27-32.

Refbacks

  • There are currently no refbacks.


Copyright (c) 2024 LI Hong wei

Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.