Research on the Risk Warning and Control of the Project Progress of Beijing Daxing International Airport

LIU Au pu, CHEN Jian guo, TANG Ke wei, SHI Qian

Article ID: 2579
Vol 2, Issue 2, 2022
DOI: https://doi.org/10.54517/vfc.v2i2.2579
VIEWS - 3076 (Abstract)

Download PDF

Abstract

Based on the theory of progress control and risk management, this paper systematically sorts out the progress risk of Beijing Daxing International Airport, discusses the general schedule and progress risk identification model and its approach, and constructs multi-level early warning and dynamic monitoring methods for progress risk. Meanwhile, the method for general schedule and progress risk management of large-scale airport projects is also studied. The practice of early warning and control of the general schedule and progress risk of Daxing Airport project has achieved good results, which provides support for the comprehensive progress control of Daxing Airport project, and guarantees the realization of the target completion time of general schedule.


Keywords

Airport project; Schedule risk; Progress deviation; Early warning; Dynamic control.


References

1. Yuan Yongbo, Yan Guodong, Wang Ailin, Zhang Mingyuan. Application of system dynamics in risk identification of construction projects[J]. Practice and Understanding of Mathematics, 2010, 40(21):99-106.

2. Wang Yujing, Li Yongkui. A large-scale complex construction project planning model based on system dynamics[J]. Industrial Engineering and Management, 2010, 15(03):87-94.

3. Chen Dongfang, Chen Jianguo. Research and application of construction project schedule early warning and its model construction[J]. Journal of Engineering Management, 2010, 24(03):318-322.

4. Shao Xiaoliang, Sheng Buyun, Wang Xinggang, Chai Zhongmin, Yao Lu. Research on multi-level project schedule risk early warning system[J]. Journal of Wuhan University of Technology (Information and Management Engineering Edition). 2015, 37(04):509-513.

5. Han Xiaokang, Niu Jia, Lu Mei. Project schedule warning and tracking feedback system construction [J]. Project Management Technology, 2018, 16 (08):26-29.

6. Li Cunbin, Lu Gongshu, Li Peng, Li Shang. A system dynamics model for schedule risk management of power grid construction projects[J]. East China Electric Power, 2012, 40(02):178-182.

Refbacks

  • There are currently no refbacks.


Copyright (c) 2024 LIU Au pu, CHEN Jian guo, TANG Ke wei, SHI Qian

Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.